DIESEL and MAV3 manufactured at the IMC site in Mestre

The project aims to obtain the "Fire Prevention Certificate" for two buildings intended for the maintenance of rolling stock, located at the IMC Trenitalia site in Mestre (VE).

For the assessment of the load-bearing capacity of the structure and any potential collapse mechanism and for the verification of evacuation conditions for the occupants, the performance-based fire safety engineering (FSE) method was used.

Various fire scenarios were defined, anticipating a fire inside a carriage during maintenance work in different positions within the buildings. Using literature data and real-scale studies, the fire curve of the carriage was defined, and evacuation times for each scenario were determined after a precise assessment of the state and various tasks of the occupants within the building. The fire was then simulated using the FDS calculation code.

Regarding the load-bearing capacity of the structure, the temperature curves acting on the load-bearing elements were defined, and the maintenance of the structure’s load-bearing capacity was verified for the entire period necessary for the evacuation of the occupants.

/